| Hoover
Dam |
|
| Industrial
World Wonders |
| Length: 1244
feet (379 m) |
| Height: 726.4
feet (221 m) |
| Construction
began: 1931 |
| Opening date:
1936 |
| Costruction Cost:
49 million |
| |
| |
Hoover
Dam from the air [1] |
Hoover Dam is a concrete
gravity-arch dam in the Black Canyon
of the Colorado River, on the border
between Arizona and Nevada. The dam,
located 48 kilometers (30 miles) southeast
of Las Vegas, is named after Herbert
Hoover, who played an instrumental
role in its construction. Hoover was
an engineer who promoted the dam,
first as Secretary of Commerce, and
later as President of the United States.
Construction began in 1931 and was
completed in 1936, over two years
ahead of schedule. The dam is operated
by the Bureau of Reclamation of the
U.S. Department of the Interior. The
dam provided jobs for many depression-era
workers and became an inspiration
for Roosevelt's Civilian Conservation
Corps (CCC) and other New Deal programs.
The gigantic size of the project stimulated
the invention of many machines, paving
the way for future large construction
projects.
Lake Mead, the reservoir
created behind the dam, is named after
Elwood Mead who oversaw the construction
of the dam. Listed on the National
Register of Historic Places in 1981,
Hoover Dam was designated a National
Historic Landmark in 1985.
History
Before the construction of the dam,
the Colorado River would periodically
overflow its banks when snow from
the Rocky Mountains melted and drained
into the river causing floods that
destroyed downstream farming communities.
In 1905, floods cut a new channel
for the river through inhabited farmland
which took 16 months to reverse. Then
the water would run off and evaporate
before crops could ripen and be harvested.
In addition to essential flood control,
a dam would make possible the expansion
of irrigated farming in the desert
region. It would also provide a dependable
supply of water for Los Angeles, Las
Vegas, and other communities in southern
California, Nevada, and Arizona, and
could provide electrical power for
over one million people.
One of the major obstacles
for the project was determining the
equitable allocation of the waters
of the Colorado River. Several of
the Colorado River Basin states feared
that California, with its vast financial
resources and great thirst for water,
would be the first state to begin
beneficial use of the waters of the
Colorado River and therefore claim
rights to the majority of the water.
It was clear that without some sort
of an agreement on the distribution
of water, the project could not proceed.
Planning and
government approval
A commission was formed in 1922 with
a representative from each of the
Basin states and one from the federal
government. The government's representative
was Herbert Hoover, then Secretary
of Commerce under President Warren
Harding. In January 1922, Hoover met
with the state governors of Arizona,
California, Nevada, New Mexico, Utah,
and Wyoming to work out an arrangement
for apportioning the waters of the
Colorado River for their states' use.
The resulting Colorado River Compact,
signed on November 24, 1922, split
the river basin into upper and lower
halves with the states within each
region deciding how the water would
be divided. This agreement, known
as the Hoover Compromise, paved the
way for the Boulder Dam Project.
The first attempt to
gain congressional approval for construction
of Boulder Dam came in 1922 with the
introduction of two bills in the House
of Representatives and the Senate.
The bills were introduced by Congressman
Phil D. Swing and Senator Hiram W.
Johnson and were known as the Swing-Johnson
bills. The bills failed to come up
for a vote and were subsequently reintroduced
several times. In December 1928, both
the House and the Senate finally approved
the bill and sent it to the president
for approval. On December 21, 1928,
President Calvin Coolidge signed the
bill approving the Boulder Canyon
Project. The initial appropriation
for construction was made in July
1930, by which time Herbert Hoover
had become President.
Early plans called for
the dam to be built in Boulder Canyon,
so the project was known as the Boulder
Canyon Project. The dam was actually
built in Black Canyon, but the project
was still called the Boulder Canyon
Project.
Contracting
Very few companies could put up a
$2 million bond required to bid on
the contract. The contract to construct
the dam was awarded to a consortium
of Six Companies, Inc., a joint venture
of Morrison-Knudsen Company of Boise,
Idaho; Utah Construction Company of
Ogden, Utah; Pacific Bridge Company
of Portland, Oregon; Henry J. Kaiser
& W. A. Bechtel Company of Oakland,
California; McDonald & Kahn Ltd.
of Los Angeles; and J. F. Shea Company
of Portland, Oregon.
Six Companies, Inc.
was also contracted to build a new
town for construction workers, to
be called Boulder City, but the construction
schedule for the dam was accelerated
in order to create more jobs in response
to the onset of the Great Depression,
and the town was not ready when the
first workers arrived at the site
in early 1931. During the first summer
of construction, workers and their
families were housed in temporary
camps in Ragtown while work on the
town progressed. Discontent with harsh
living conditions and dangerous working
conditions led to a strike on August
8, 1931. Six Companies responded by
sending in strike-breakers with guns
and clubs, and the strike was soon
quashed. But the discontent prompted
the authorities to speed up the construction
of Boulder City, and by the spring
of 1932 Ragtown had been deserted
.
While working in the
tunnels, many workers suffered from
the carbon monoxide generated by the
machinery there, including trucks
that were driven in. The contractors
claimed that the sickness was pneumonia
and was not their responsibility.
Some of the workers sickened and died
in nearby hospitals because of the
so-called "pneumonia." Those
who died off the site were not counted
on the official death list.
Most workers were paid
$4.00 per day and the "high-scalers"
who risked their lives climbing on
the high cliffs were paid $5.60 per
day. These were good wages in the
depression era.
Construction
Preparation
To isolate the construction site,
and protect it from flooding, two
cofferdams were constructed. To divert
the river's flow around the construction
site, four tunnels (called spillways)
were driven through the canyon walls,
two on the Nevada side and two on
the Arizona side. These tunnels were
56 feet (17 m) in diameter. Their
combined length was nearly 16,000
feet (4880 m, more than three miles).
Tunneling began at the lower portals
of the Nevada tunnels in May 1931.
Shortly after, work began on two similar
tunnels in the Arizona canyon wall.
In March 1932, work began on lining
the tunnels with concrete. First the
base or invert was poured. Gantry
cranes, running on rails through the
entire tunnels were used to place
the concrete. The sidewalls were poured
next. Moveable sections of steel form
were used for the sidewalls. Finally,
using pneumatic guns, the overheads
were filled in. The concrete lining
is 3 feet (914 mm) thick, reducing
the finished tunnel diameter to 50
feet (15 m).
Construction of the
upper cofferdam began in September
1932, even though the river had not
yet been diverted. A temporary horseshoe-shaped
dike protected the cofferdam on the
Nevada side of the river. After the
Arizona tunnels were completed, and
the river diverted, the work was completed
much faster. Once the cofferdams were
in place and the construction site
was dry, excavation for the dam foundation
began. It was necessary to remove
all loose material until solid rock
was reached to provide a firm foundation
for the dam. Work on the foundation
excavations was completed in June
1933. During excavations for the foundation,
approximately 1,500,000 yd³ (1,150,000
m³) of material was removed,
including material that was the result
of canyon wall stripping operations.
Concrete pouring
The first concrete was placed into
the dam on June 6, 1933. Since no
structure the magnitude of Boulder
Dam had ever been constructed, many
of the procedures used in construction
of the dam were untried. One of the
problems that faced the designers
was cooling and contraction of such
large amounts of concrete in the dam.
Rather than being a single block of
concrete, the dam was built as a series
of interlocking trapezoidal columns
in order to allow the tremendous heat
produced by the curing concrete to
dissipate. Engineers calculated that
if the dam were built in a single
continuous pour, the concrete would
have gotten so hot that it would have
taken 125 years for the concrete to
cool to ambient temperatures. The
resulting stresses would have caused
the dam to crack and crumble away.
It was decided to pipe
refrigerated water through tubes in
the wet concrete to remove the heat
generated by the chemical reactions
that solidify the concrete. Such a
large refrigeration project was beyond
the expertise of Six Companies, Inc.,
and Union Carbide Corporation was
contracted to assist with the refrigeration
part of the project. In order to speed
up the concrete cooling so that layer
could be poured more quickly, each
form contained cooling coils of 1
inch (25 mm) thin-walled steel pipe.
When the concrete was poured, river
water was circulated through these
pipes. After an initial cooling, chilled
water from a refrigeration plant on
the lower cofferdam was circulated
through the coils to finish the cooling.
As each block was cooled, the pipes
of the cooling coils were cut off
and pressure grouted with pneumatic
grout guns.
Power plant
Generators on the Nevada Wing of the
Hoover Dam Power PlantExcavation for
the powerhouse was carried out in
conjunction with excavations for the
dam foundation and abutments. Excavations
for the U-shaped structure located
at the downstream toe of the dam were
completed in late 1933 with the first
concrete placed in November 1933.
Generators at the Dam's Hoover Powerplant
began to transmit electricity from
the Colorado River a distance of 266
miles (364 km) to Los Angeles, California
on October 26, 1936. Additional generating
units were added through 1961. Water
flowing from Lake Mead through the
gradually-narrowing penstocks to the
powerhouse reaches a speed of about
65 miles per hour when it reaches
the turbines.
The seventeen main turbine-generator
combinations at this powerhouse generate
a maximum of 2,074 megawatts of hydroelectric
power. All hydroelectric plants generate
a controlled, variable amount of power
as the demand for power varies during
a day. In fact, a big advantage of
hydroelectric power is the ability
to quickly and readily vary the amount
of power generated, depending on the
load presented at that moment. Steam-driven
power plants are not so easily "throttled"
because of the amount of thermodynamic
inertia contained in their systems.
Even though water control,
not power generation, is the main
purpose of the dam, the dam construction
and maintenance has been fully paid
for through the sale of electricity
from the dam.
Architectural Style
The initial plans for the finished
facade of both the dam and the power
plant consisted of a simple, unadorned
wall of concrete topped with a Gothic-inspired
balustrade and a powerhouse that looked
like little more than an industrial
warehouse. This initial design was
considered too plain and unremarkable
for a project of such immense scale,
so Los Angeles-based architect Gordon
B. Kaufmann was brought in to redesign
the exteriors. Kaufmann greatly streamlined
the buildings, and applied an elegant
Art Deco style to the entire project,
with sculptured turrets rising seamlessly
from the dam face and clock faces
on the intake towers set for Pacific
and Mountain time zones. Hoover Dam
today is considered one of the finest
examples of Art Deco anywhere in the
world.
Use for road
transport
Aerial shot of Hoover DamThe Hoover
Dam also serves as a crossing for
U.S. Route 93. This will change by
2008 when the Mike O'Callaghan-Pat
Tillman Memorial Bridge is completed
as part of the Hoover Dam Bypass Project.
The section of U.S.
Route 93 that approaches and crosses
Hoover Dam is woefully inadequate
for the increased vehicle traffic
of today. It is one lane in each direction,
has several narrow and dangerous turns,
has poor sight distances, pedestrian
crossings, and an occasional rock
slide. Following the September 11,
2001 terrorist attacks, truck traffic
over the Hoover Dam has been diverted
south to a Colorado River crossing
near Laughlin, Nevada in an effort
to safeguard the dam from hazardous
spills or explosions. The bypass and
the bridge are intended to improve
travel times, replace the dangerous
roadway, and reduce the threat of
an attack or a potential accident
at the dam site.
Construction of Hoover
Dam